Art Room Renovation
The Art Room Renovation has many moving parts and each stage is broken down below. We are excited to continue updating this page as stages finish.
Empty the Room
The room after all remaining woodshop items had been removed. Thanks to our maintenance and to Mel Getty for clearing the room.




Phil Yeo Contracting
Phil Yeo retrofitted the existing cupboards that were in place to have level shelving. His team painted the walls and put down a new floor.




TD Logan Plumbing
Water lines were brought across the hall through the concrete and ceiling to place a new sink in the room. This sink has a filtration system that will filter sediment out and keep our system running clean.


TA Thomson Electrical Contracting
Devin updated the electrical outlets by the new sink. He also installed new lighting that better suited an art room. Outlets in the floor were removed, exposed wires were capped off, and the power restored.